Concrete Pad Calculator

Calculate exactly how much concrete you need for any slab -- patios, driveways, garage floors, and more. Get cubic yards, bag counts, and a complete shopping list.

Concrete thickness standards are set by engineering organizations with decades of field research behind them. Getting the depth right on your first pour prevents costly cracking and premature failure.

ASTM C94/C94M sets how ready-mixed concrete is batched, measured and delivered, but it does not fix one default strength for every pour. Quality requirements are either those stated in the specification or those ordered by the buyer, and where the two differ, it is the purchaser's own specification that governs.

-- ASTM International, C94/C94M Standard Specification for Ready-Mixed Concrete

That one line is why the number on your delivery ticket matters more than any blanket figure you read online. C94/C94M is an end-result specification. It tells the plant what to prove, not what to pour. You name the strength when you order, and for most residential work that lands between 3,000 and 4,000 psi at 28 days. A plant will batch weaker if nobody says otherwise.

Source: ASTM C94/C94M, explained in NRMCA Concrete in Practice -- nrmca.org

The American Cement Association, which represented U.S. cement manufacturers as the Portland Cement Association from 1916 until it renamed in May 2025, puts the residential baseline at four inches of non-reinforced pavement for passenger-car driveways, stepping up to five inches wherever heavier vehicles park.

-- American Cement Association (formerly Portland Cement Association)

Four inches is a floor, not a target. That extra inch raises load-carrying capacity by roughly half, which is cheap next to tearing out a cracked slab. Subgrade prep and joint spacing decide as much as thickness does, so do not spend the money on depth and then skip compaction.

Source: American Cement Association -- cement.org

🏗 PAD CALCULATOR

Pad Thickness by Equipment Type

How thick should your concrete slab be? Code-recommended dimensions for any project
Application Min Thickness Recommended Reinforcement
Sidewalk / Walkway3.5"4"Optional fiber
Patio4"4"Mesh recommended
Residential Driveway4"5"Mesh or rebar grid
Garage Floor4"5-6"Rebar grid required
RV/Truck Pad6"6-8"Heavy rebar grid
Shed Foundation (small)4"4"Mesh
Pool Deck4"4-5"Mesh + control joints
Hot Tub Pad4"6"Rebar grid

For freeze-thaw climates (Northeast, Midwest, Mountain West), add 1 inch to the recommended thickness. Always check your local building code -- some jurisdictions require 6" minimum for driveways regardless of use.

Pad Pour Checklist

A repeatable order-of-operations that prevents the most common DIY slab mistakes
  1. Excavate to depth. Slab thickness + base depth + 2" for forms = total dig depth. For a 4" slab on 4" base, dig 10" below final grade.
  2. Compact subgrade. Native soil should be compacted to 95% before adding base. Don't skip this on clay or recently disturbed soil.
  3. Lay 4" of crushed stone or roadbase. Compact in 2" lifts. 95% compaction is the target.
  4. Set forms. 2x4 lumber for 3.5" slabs, 2x6 for 5" slabs. Stake every 4 feet. Check for level and proper slope (¼" per foot away from buildings).
  5. Place vapor barrier and reinforcement. 6 mil poly under interior slabs. Wire mesh or rebar grid raised 1.5-2" off the base on chairs.
  6. Pour and screed. Pour from far end working back. Screed level with the forms using a 2x4. Don't over-work the surface.
  7. Float, edge, and joint. Bull float once water sheen disappears. Edge the perimeter with an edging tool. Cut control joints every 8-10 feet.
  8. Final finish and cure. Broom finish for traction or trowel for smooth. Cover with plastic for 7 days minimum, lightly mist daily.
  9. Wait before loading. Foot traffic 24-48 hours. Vehicles 7 days. Heavy equipment 28 days.

Common Concrete Pad Sizes and Costs

Reference for AC pads, hot tub pads, generator pads, shed foundations, and RV pads
Pad Type Typical Size Thickness Yards 80lb Bags Est. Installed Cost
AC / HVAC Unit Pad3 × 3 ft4"0.124 bags$75-$200
Generator Pad4 × 6 ft4"0.3310 bags$150-$400
Hot Tub / Spa Pad8 × 8 ft6"1.3240 bags$400-$900
Shed Foundation (small)10 × 12 ft4"1.6349 bags$500-$1,200
Shed Foundation (large)12 × 20 ft4"3.30ready-mix$900-$2,200
RV Pad (single)12 × 40 ft6"10.97ready-mix$2,500-$5,500
Basketball / Sports Pad30 × 60 ft4"24.44ready-mix$6,000-$15,000

Concrete Pad Reinforcement Guide

When you need rebar, wire mesh, or nothing -- and exactly how to install it
No reinforcement

Small pads under 25 sq ft with light loads: AC unit pads, generator pads on stable soil. These are small enough that the concrete mass itself provides adequate strength.

Wire mesh (6×6 WWF)

Pads 25-100 sq ft with light to moderate loads: small shed floors, patio sections, equipment pads. Elevate mesh 1.5" off the base using wire chairs so it sits at mid-depth in the slab.

#4 Rebar grid

Hot tubs, large sheds, RV pads, anything over 100 sq ft or carrying concentrated loads. Use #4 rebar on 18-inch centers in both directions, elevated 2 inches off base. All corner bars must overlap 12 inches minimum.

Reinforcement does not prevent cracking -- it keeps cracks tight when they occur. Proper subgrade preparation (compacted base + gravel) and control joints do more to prevent cracking than reinforcement does. Think of rebar and mesh as insurance, not a substitute for good prep work.

Pad Pour: Truck vs Short Load

Concrete weighs 4,000 lbs per cubic yard. Here is what your truck can legally carry.
2026 Truck Max Payload Concrete Capacity Bag Capacity (80lb)
Toyota Tacoma (standard)1,521 lbs~0.38 cu yd~18 bags
Toyota Tacoma (i-FORCE MAX)1,705 lbs~0.42 cu yd~21 bags
Ford F-150 (PowerBoost Hybrid)1,740 lbs~0.43 cu yd~21 bags
Ford F-150 (5.0L V8)2,235 lbs~0.55 cu yd~27 bags
Ford F-150 (3.5L EcoBoost)2,440 lbs~0.61 cu yd~30 bags
3/4-ton (F-250, Silverado 2500)3,500+ lbs~0.87 cu yd~43 bags

*Payload values from 2026 manufacturer specs. Your actual payload is on the door-jamb sticker. Add accessories (toolbox, bedliner) and that number drops 100-300 lbs. A driver and passenger count against payload too.

If your project needs more than 1 cubic yard (4,000 lbs), pickup-truck delivery requires multiple trips. For 2+ cubic yards, ready-mix delivery is almost always cheaper than the gas, time, and suspension wear of multiple bag runs. Most ready-mix trucks deliver 8-10 yards in one trip.

Concrete Pad FAQ

Common questions about calculating and pouring concrete slabs

How thick should a concrete pad be?+

Standard pads for patios, sheds, and light equipment use 4-inch thickness. Hot tub pads and heavy equipment pads should be 6 inches. RV pads, boat pads, and areas with heavy vehicular traffic need 6-8 inches. Always use rebar or wire mesh reinforcement for pads over 4 inches.

How much does a concrete pad cost?+

Material cost for a concrete pad runs $3-$5 per square foot for bags or $4-$7 per square foot for ready-mix. Installed cost (professionally poured) averages $6-$12 per square foot depending on region. A 10×10 pad runs $600-$1,200 installed; a 12×20 pad runs $1,440-$2,880 installed.

Do I need rebar in a concrete pad?+

For pads under 6 inches thick supporting light loads (AC unit, generator, patio furniture), wire mesh is sufficient. For hot tub pads, equipment pads, or anything over 6 inches, use #3 or #4 rebar on a 12-inch grid. Always elevate reinforcement 1.5-2 inches off the ground using plastic chairs.

How long does a concrete pad take to cure?+

Concrete reaches 70% strength in 7 days and full strength (3,000-4,000 PSI) in 28 days. You can walk on a pad in 24-48 hours. Light equipment can go on it at 7 days. Heavy equipment, vehicles, or hot tubs should wait the full 28 days. Keep the pad moist (spray daily or cover with plastic) during the first 7 days for maximum strength.

What size concrete pad do I need for a hot tub?+

Most hot tubs need a pad at least 2 feet larger than the tub on each side. A 7×7 foot hot tub needs at least a 9×9 foot pad. Thickness should be 6 inches to support the weight (a filled hot tub can weigh 5,000-6,000 lbs). Use #4 rebar on a 12-inch grid and 4,000 PSI concrete.

How much concrete do I need for an AC unit pad?+

A standard 3×3 foot AC pad at 4 inches thick requires only 0.11 cubic yards -- about 4 bags of 80lb concrete. Some contractors use pre-cast AC pads instead of pouring, which eliminates the wait time and costs $30-$80. For a 3×4 foot pad, you'll need 5-6 bags.

Last updated . Formulas reviewed by Joe R., Masonry Specialist, and Elena S., Civil Engineer (PE). Spotted a number that looks wrong? Report a Data Error and we will re-verify it against the source.